The economic benefit of manifolded duct can be seen in the following example, taken from an actual Hospital case study.
Scenario 2 - Loose Erector Set
In the above, the Loose Erector Set has 9 times as many pieces to off-load (9 versus 1) and 3 times the amount of field joints/cuts to perform (18 versus 6). The economic impact of these two different configurations is shown in the table below.
| |
|
|
|
|
| |
Case Study Example: Seven Floor Hospital |
|
|
|
| |
|
|
|
|
| |
Total Duct Installed Cost |
$170,000 |
100% |
|
| |
|
|
|
|
| |
Actual Field Joints Required (Loose Erector Set) |
1,796 |
100% |
|
| |
Actual Field Joints Required (Manifolded) |
1,289 |
72% |
|
| |
Field Joints Saved with Manifolded |
507 |
28% |
|
| |
|
|
|
|
| |
Total Man-hours Saved |
689.25 |
|
|
| |
Field Labor Cost (per hour) |
$32.69 |
|
|
| |
|
|
|
|
| |
Manifolded Cost Savings |
$22,532 |
13% |
|
| |
|
|
|
|
The elimination of 507 Field Joints resulted in a savings 689 man-hours or $22,532. With the cost of field labor soaring and an opportunity to save up to 30% of your field joint labor, how can you afford not to consider Manifolded Duct? |
 |
|