The economic benefit of manifolded duct can be seen in the following example, taken from an actual Hospital case study.

Scenario 1 - Manifold

Scenario 2 - Loose Erector Set

In the above, the Loose Erector Set has 9 times as many pieces to off-load (9 versus 1) and 3 times the amount of field joints/cuts to perform (18 versus 6). The economic impact of these two different configurations is shown in the table below.

         
 
Case Study Example: Seven Floor Hospital
   
 
   
 
Total Duct Installed Cost
$170,000
100%
 
 
 
 
Actual Field Joints Required (Loose Erector Set)
1,796
100%
 
 
Actual Field Joints Required (Manifolded)
1,289
72%
 
 
Field Joints Saved with Manifolded
507
28%
 
 
 
 
Total Man-hours Saved
689.25
 
 
Field Labor Cost (per hour)
$32.69
 
 
 
 
Manifolded Cost Savings
$22,532
13%
 
         

The elimination of 507 Field Joints resulted in a savings 689 man-hours or $22,532. With the cost of field labor soaring and an opportunity to save up to 30% of your field joint labor, how can you afford not to consider Manifolded Duct?

Product Library

Select a category 

Lucas Oil Stadium (83 kB) pdf
Description: Spiral Duct Gets SUPER-SIZED for New Lucas Oil Football Stadium in Indianapolis, IN

  *
*
*
*
Feedback Questions and Comments?
© 2007 SEMCO Incorporated, a Fläkt Woods Company | Legal